23/00658/AOC
|
22/00542/LBC - Condition 3 - Materials (discharge of condition)
|
Pear Tree Cottage High Street Turvey Bedford Bedfordshire MK43 8DE
Grant Permission
Received
Thu 23 Mar 2023
Validated
Thu 23 Mar 2023
Consultation
Tue 12 Sep 2023
Recommendation and/or Committee
Decided
Mon 18 Sep 2023
| Application Received Date | Thu 23 Mar 2023 |
|---|---|
| Application Validated Date | Thu 23 Mar 2023 |
| Overall Consultation Expiry Date | Tue 12 Sep 2023 |
| Actual Committee Date | Not Available |
| Latest Neighbour Consultation Date | Not Available |
| Neighbour Comments should be submitted by Date | Not Available |
| Latest Statutory Consultee Consultation Date | Tue 29 Aug 2023 |
| Statutory Consultee Consultation Expiry Date | Tue 12 Sep 2023 |
| Last Advertised In Press Date | Not Available |
| Latest Advertisement Expiry Date | Not Available |
| Last Site Notice Posted Date | Not Available |
| Latest Site Notice Expiry Date | Not Available |
| Target Date | Thu 18 May 2023 |
| Agreed Extension to Statutory Determination Deadline | Not Available |
| Decision Made Date | Mon 18 Sep 2023 |
| Decision Issued Date | Mon 18 Sep 2023 |
| Permission Expiry Date | Not Available |
| Decision Printed Date | Mon 18 Sep 2023 |
| Environmental Impact Assessment Received | Not Available |
| Statutory Determination Deadline (Unless there is an Agreed extension date above) | Thu 15 Jun 2023 |